Following the successful completion of the project at Thistle Bloomsbury Park Hotel, we have now commenced work at the Royal Horse Guards Hotel. We collaborate closely with the hotel to minimise disruption to guests, ensuring that only certain areas of each floor are closed at a time. Over the course of this 8-month project, we replaced more than 700 fire doors, including all the hotel bedrooms, and completed extensive fire-stopping works. Each phase was completed within a strict deadline, allowing the hotel to continue operating smoothly and without affecting guest bookings
PROJECT DETAILS
CONTRACTOR
Clermont Hotel Group
PROJECT TYPE
Commercial
PROJECT VALUE
£2,200,000